Notes for September
Week of 9/1
Hang drywall
Radiance Barrier (rafter insulation)
Start Bricking (front)
Lot, West Side
Lot, East Side
Bricking House
Radiance Barrier
Week of 9/8
Bricking continues (front)
Tape and bed sheetrock, begin texturing
Cabinets installed (
errors
)
Got contract on current house
Lot, West Side
Lot, East Side
Front almost done
East side
One Car Garage
Kitchen Cabinet South Upper
Kitchen Cabinet South Lower
Kitchen Cabinet Island
Master Bathroom Cabinet
Bedroom #2 Dressing Cabinet
Week of 9/15
Bricking continues (west and back)
Glass Block window, Master bath
Interior Trim (doors, base molding)
Attic Insulation (blown fiberglass)
Garage doors installed
Lot, West Side
Lot, East Side
Lot, Front
Glassblock Window
Fireplace Mantle
Stair Rail being built
Mess in garage
Week of 9/22
Finish bricking
More trim, stair work
Bathroom sinks
Back patio poured
Lot graded
Lot, West Side
Lot, East Side
Backyard, West
Backyard, East
Sink, Bedroom 2 dressing
Sink, Master bathroom, West
More brick delivered
Stair rail
Upstairs floor decking screwed down
Back Patio poured
Back of house bricked
Stair rails
Lot, after grading
Lot, East approach
Week of 9/29
Interior Painting (
wrong color
)
Tile installation
Tree removal
Lot, West Side
Lot, East Side
Mantle
Trees to remove