Notes for August


    Additional framing.  Shingles installed 8/4
Post tension cables in foundation stressed to 32,000 pounds per square inch 8/6
Plumbing work started. HVAC work started
Termite pre-construction treatment done (green tinge on boards)
Siding installed where brick won't be (back side family room)

    Finish plumbing, Finish HVAC,  Electrical  rough in, non brick areas painted Saturday

    Pre-wire for Security, Phone, TV
Driveway poured 8/19, Correct Brick Delivered!!
Various Framing fixes
Put current house on market

    Sidewalks, walkway poured (8/26)
Wall (bat) insulation installed
Pre-drywall walkthrough with builder (8/29)
Heather and I insulated the exterior walls both garages
We cleaned up the old (wrong) brick from the front yard to prevent it from getting mixed in when bricking begins (we saved brick for future projects)

 

 